Project Overview
Located in Mhasale village, Sakri Taluk of Dhule District in Maharashtra, the project envisions to harness the abundant solar resource and convert it to green electricity by using Mono PERC Crystalline – MBB Technology. The 220 KV Grid Substation where power will be evacuated from the Project is located in Shivajinagar village, Sakri at ~11 km distance from the Project site. The substation is surrounded by agricultural land and the TL route passes predominantly through agricultural lands in the villages of Bhadgaon, Bhamer and Vardharne.
The total estimated land required for the Project is 380.8 ha
The estimated commissioning dates are as below:
- AMPYR 12 – 50 MW in Mar 2025;
- AMPYR 12A -50 MW in May 2025;
- AMPYR 12 A -50 MW in July 2025; and
- AMPYR 12 A -50 MW in September 2025